New Construction » Twenty Wells Elementary

Twenty Wells Elementary

11/19/2021
  • All of the interior concrete has been placed except for the stage.
  • Exterior masonry has started and they are nearly complete on two classroom wings.
  • Supply chain issues have us waiting to get the steel joists and deck.
  • The mechanical room walls have been started.
  • Boilers will arrive this month.
 
11/1/2021
  • All Footings and foundation is complete.
  • Nearly all of the floor slabs are placed. The kitchen and boiler room are still finishing up some underground and should be complete by mid-November.
  • Interior masonry walls are complete in two wings and almost done in the 3rd. 
  • Exterior masonry walls will begin this week. 
  • Site utilities are continuing to be placed.
  • Supply chain issues have delayed the delivery date of the steel joist and deck into January.
  • Right now we are still anticipating being ready to open in August but it will be a push to get there. 
  • We have changed some materials in the building that will allow us to make up some of the time lost with the delay of the joist and deck.